Tuesday, November 27, 2012

FG Wilson On the Ball Powering Aviva Stadium

As one of the leading global manufacturers of gas and diesel generator sets, sporting arenas and stadiums are increasingly turning to FG Wilson (Engineering) Ltd, to ensure that their programme of sporting and music events run without a hitch.

The Aviva Stadium in Dublin, formerly Lansdowne Road, is a world class venue for rugby, football, concerts and business conferences and everything from the scoreboards and the floodlights to the under pitch heating is powered by FG Wilson generators with a 6.8 MVA power rating. FG Wilson has installed power generation sets and runs ongoing maintenance contracts at other stadiums including Croke Park, Casement Park and Thomond Park.

In its original incarnation, Lansdowne Road stadium was the oldest sports stadium in Europe but after a complete rebuild programme in 2007, the 50,000 all-seater Aviva Stadium re-opened in August 2010.

FG Wilson, invited to tender for the power supply through the main contractors Kentz, secured the order due to their technical expertise in ensuring the delivery of a bespoke solution that was integral to the look and feel of the finished structure and their early involvement with the stadium redevelopment.

Immediately FG Wilson identified that to deliver the power requirements of this site, four 1,700 kVA generator sets would be required. In concealing the generators in a very compact space underneath the stadium seating (level 7), the aesthetics of the stadium remained intact and prevented the need to house them externally in a storage facility, as is often the case. All air-handling, cooling systems, exhaust units and switchgear were also concealed within the envelope of the stadium's expansive seating racks. In conjunction with the project architect, the exhaust system was moulded into polycarbonate blades of the surface structure of the stadium meaning no protrusions or exposure to rainwater. The exhaust is fitted with its own drainage system to keep rainwater out.

During stadium events, the generator sets operate in parallel with the ESB mains supply to supplement the stadium's power demand and also deliver no break standby power on mains failure.

In order to deliver this control philosophy FG Wilson designed a fully integrated control system, based on the Allen Bradley Hot-standby PLC platform. This delivered a high level of system redundancy and greatly increased the operational security of the stadium.

The timing of the installation of the generator sets was critical as they needed to be in situ prior to the fixing of the seating racks above them. Any delay in the positioning would have had impacts on the timeline for the seating construction above. This part of the project was completed to schedule so enabling the further smooth running of the stadium build.

Another challenge overcome by FG Wilson was noise. The Aviva Stadium is surrounded by residential properties and the power product solution had to guarantee extremely low noise levels. This was set at 53 dBA at 1m, which is low for this type of installation, but as the surrounding area is a highly desirable residential development, minimal noise was critical to the overall success of the scheme.

To ensure noise levels were correct the generators were set on spring based anti-vibration pads. This means that there is no vibration translation to the structure of the building when the power supply is on as the generators are effectively isolated from the structure itself.

Another advantage presented by FG Wilson is that all external contractors on site, from burger vans to merchandise sellers to event crews, can access the stadium's power supply rather than bringing their own generators onto the site. This was not previously possible. The capacity provided by FG Wilson's generators is 5.44 MW and at peak usage the Aviva Stadium uses on average 3.5 MW. The generators have a local 24 hr hour daily service fuel tank, supplied from a large bulk fuel storage tank to provide multiple day 100% load run autonomy.

The power solution presented by FG Wilson also has an environmental benefit in the form of a heat recovery facility. From the jackets surrounding the engines up to 750 kw of heat is 'recovered' from each machine and used to heat the pitch and provide other forms of heating around the stadium.

The installation programme, which took 11 months from tendering to completion, was completed on time and within budget ahead of the opening game in August 2010. Since then, hundreds of football and rugby matches, concerts and events have taken place with Madonna having played there recently to a capacity crowd.
David Blennerhassett, Dealer principal at FG Wilson in Dublin said: "This was a very challenging stadium project which presented a number of issues from a noise, space and design perspective. But in getting to grips with the project from an early phase and working with the M & E Consultants throughout the tendering process we were able to deliver a reliable, competitive and quality power product that exceeded all initial expectations. We had a lot of positive input from the initial stages, which was instrumental in determining the final solution.  The Aviva Stadium was an immensely satisfying project of which we are extremely proud and as part of our ongoing maintenance programme we always ensure that we have a representative on site every time there is an event taking place."

Wednesday, November 7, 2012

FG Wilson Powering the Olympic Park

Olympic Games Opening Ceremony
The London Olympic Games 2012 may be over but the leading manufacturer of diesel and gas generator sets, FG Wilson, is ensuring that the legacy of the spectacular multi-million pound event site continues. Having provided generator sets to power the events at three of the Olympic Park's eight venues - the Aquatics Centre, IBC Media Centre and the Olympic Stadium - they are now contracted to provide ongoing support and maintenance for the next year.

The project, which is being delivered by Bells Controls and Equipment Ltd - an official FG Wilson UK Dealer - began in 2008 and is worth over £500,000.

London 2012 has been the catalyst for transforming 2.5 square kilometres of industrial land in east London into the 490 acre Olympic Park which has changed the landscape irrevocably.

The power solution delivered by Bells consisted of a 635kVA and 730KVA generator for Life Safety Services within the main stadium. Both generators were housed in bespoke enclosures designed to achieve a noise level of NR 50 at 5 metres. The enclosures also featured an exhaust flue extension that discharged within the outlet attenuator, providing exhaust gas dilution.

At the IBC Media Centre, a complex 24-hour media hub for around 20,000 broadcasters, photographers and journalists, featured a 200kVA generator within a specially designed enclosure rated at 65dBA at 1 metre. The enclosure was positioned on the roof of the building and also featured an internal fuel system, which was installed inside the structure. The fuel pipe solution installed used an innovative flexible pipe in pipe system rather than traditional mild steel welded pipe in pipe, facilitating a quicker installation. At the Aquatics Centre, one of the permanent venues specially constructed for London 2012, and the site of Team GB's three medal victory, a 350kVA generator set was installed. The generator set was housed within a bespoke enclosure rated at 60dBA at 1 metre within the plant room, including all of the necessary ventilation ductwork and flue pipe work. The system was also used throughout the Aquatics Centre.

Robert Scott, regional sales manager UK at FG Wilson, commented: "The project has been a huge success and it has been a privilege to be involved with the Olympic Park legacy. Careful planning, design, engineering and attention to detail has been central to ensuring the success of this project. The athletes may have gone home but Bells will continue to provide ongoing services to the venues at the site under the current contract."

James Murphy Director of Bells Control said: "We were delighted to win the Olympic Park project after a very detailed and competitive tendering process. It has been a challenging project due to a number of factors including the sheer size of the venue, as well as the high level security constraints and low noise levels required, but we have successfully implemented resilient, high power solutions which meet the individual requirements of the respective venues."